Specification sheets often carry a line reading "load-bearing base 120 × 61 × 1.5" with no units and no explanation. The three figures are: 120 mm high, 61 mm wide 1.5 mm wall thickness It looks like an accessory detail, but it decides whether the whole row of niches stands steady, whether ground moisture climbs into the bottom tier, and whether mop water reaches the lowest carcass.

120: the height — the clear space from the floor to the underside of the first carcass.
61: the section width in the depth direction matched to the upright size and the carcass depth.
1.5: wall thickness, usually 1.5 mm galvanised sheet folded to section with one transverse stiffener inside.
Take away any one of the three and the base stops being a load-bearing element and becomes a mere spacer. Some quotations say only "base" without the numbers and what arrives is a 1.0 mm pad with no stiffener — identical in appearance half the load capacity.
The taller the base, the more material it uses. So why 120? Three reasons.
Splash. A columbarium floor gets mopped, and mop water spreads sideways along the floor. Below 80 mm, water easily reaches the lower edge of the bottom carcass, which is exactly where galvanised cut edges cluster — and where rust starts. 120 mm clears normal splash height.
Levelling. A columbarium floor is never perfectly flat. The standard calls for no more than 3 mm deviation under a 2 m straightedge, and real construction often runs 5–8 mm. The base must leave room for levelling shims and adjusting bolts — at least 30–40 mm. 120 minus the 80 mm splash allowance leaves exactly 40.
Ventilation. Leaving a void between base and floor lets air move and reduces moisture rising straight from the slab into the carcass. On a ground floor or in a basement, the floor is the largest cold surface in the room; a niche sitting directly on it will condense on its underside.
61 is not a round number; it has a specific relationship. The width must be slightly greater than the upright section so the upright sits fully supported rather than overhanging, and it must not be so wide that it intrudes into the aisle.
Common upright sections are 40 × 60 or 50 × 50. A base of 61 mm width with the upright centred leaves 0.5–5 mm each side, welded or bolted. If the base is 50 wide and the upright 60, the upright overhangs 5 mm on each side and the whole load runs through the weld — which will crack over time.
This is checkable on the drawing: if the upright section and the base width do not correspond, the modules have been assembled from parts rather than designed as a set. It is one way to tell whether the structural components of a columbarium are a system.
The base is where the load of an entire row begins transferring the weight of every carcass, urn and door panel into the floor.
Take eight tiers at 30 kg each: total load at one upright position is about 240 kg, all of it landing on the base. Folded into a channel section, 1.5 mm galvanised gives a safety factor of about 2.5 under that load; 1.2 mm gives about 1.6, which is low.
Going from 1.2 to 1.5 raises material cost about 25%, which usually comes to under a hundred yuan per niche. That is very good value — once the base is installed it is practically impossible to replace, and replacing it means dismantling the row.

The base is a long, thin folded part, and its span direction is where it buckles. One transverse stiffener in the middle divides the long span into two short ones and raises bending capacity roughly threefold.
It usually sits at mid-length, between the uprights. At handover, shine a torch inside the base: a visible fold line is the stiffener. If there is none, either it was omitted or it was placed at the ends, which amounts to the same thing.
One detail: the stiffener must run full height, folded from top face to bottom face. A half-height rib only stiffens locally and achieves little.
One, is it sitting on the floor? Try a feeler gauge or a business card into the gap between base and slab. More than 2 mm means it is not levelled.
Two, push it. Put your palm on the top carcass and push. The row should flex slightly without rocking. Rocking means something is unfixed — base to floor, or base to upright.
Three, look at the bolts. Floor fixings should be expansion bolts at no fewer than two per metre. Adhesive alone comes loose in three to five years.
Four, look at the cut edges. Has the lower edge been touched up with anti-rust paint? This is the most overlooked location and the first to rust.
Q: Can the base be omitted and the carcass sit directly on the floor?
A: No. Without it the bottom tier condenses, mop water reaches the cut edges, and the row cannot be levelled. The bottom tier is the most failure-prone position in any columbarium.
Q: Can 120 mm be raised to 150?
A: Yes, but check the total height. Overall height is limited by the clear ceiling, so adding 30 mm at the base may cost you a tier.
Q: What if the base rusts?
A: Surface white rust can be ground back and recoated with zinc-rich paint. Structural rust-through — more than 10% of the area — requires replacing the whole section, which is major works.

The 120 × 61 × 1.5 load-bearing base does three jobs: it transfers weight to the floor, it keeps ground moisture at ground level, and it holds mop water away from the carcass. It is the least visible and least replaceable component in a columbarium. When you inspect a site crouch down and shine a torch inside the base — it tells you more about the build quality of that row than ten door panels will.